LHG:SARA Project: Difference between revisions

From Kordeus Wiki
Jump to navigation Jump to search
Jagodapejovic (talk | contribs)
Jagodapejovic (talk | contribs)
Line 837: Line 837:
|M
|M
|100%
|100%
|➡️ status update, in testing  
|in testing  
|-
|-
|[[LHG:ONERES Interface|Interface to ONERES]] (GAV) Specification
|[[LHG:ONERES Interface|Interface to ONERES]] (GAV) Specification

Revision as of 08:44, 14 April 2026

Phase 1 - SARA Fundamental

Current Project Plan

Rel. Size 2024 2025 2026 Abs.

Est-Size

Dev

Progress

External Dep.

Notes

Team Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Peparatory work 4 Discovery Discovery 5 100%
Kickoff / Initially planned discovery Def S 100%
Architecture & Shared Logic Hubs Discovery Re-Discovery XL 100%
Administration tools 8 Dis. Dev Discovery Dev QA Dev QA Dev QA Dev QA 18 85,8%
Definition / Discovery Def Dev Re-Discovery L 100%
LH Admininistration Tools Mixed Dev QA L 100%
MOC Administration Tools Mixed Dev QA L 100%
SLHs (TravelCarrierDataDistribution & OperationCenterPAXExchange BE Dev QA L 100%
Minor extensions during further discovery Mixed Dev QA S 100%
SLH - TravelCDDD

SLH - OCPAXE extensions due to feedback

Dev S 100%
Minor extensions during feedback sessions (limitations) Mixed Dev QA S 100%
Automation Engine Admin Mixed Dev Dev QA L 15% Repriorized
Passenger Portals 28 Dev QA Dev QA 11 90,9%
PAX funcationality in PAX.Portal for LH FE & BE Dev QA XL 100%
SLH - PortalUsageInteraction BE Dev L 100%
Full PAX.Portal for Discover FE Dev QA M 90%
TP-Employee features Mixed Dev Conf QA M 75% ➡️ status update
SARA.Core 40 Dis. Discovery Dev QA 20 84,5% Delayed
Initial definition of BE (like SWISS) Mgmt Def S 100%
Full SAM process discovery Mgmt Discovery XL 100%
UI/UX Iteration MgMt Dev M 100%
SARA.Core App Development Mixed Dev XXL 90%
SLH - TravelServiceManagementEcosystem BE Dev XL 100% ➡️ status update (status: in testing)
SARA.ProcessAutomationEngine BE Dev QA XL 45%
SARA.DeliveryPartnerPortal 8 Discovery Dev QA 3 95,0%
Delivery Partner Portal Mixed Discovery Dev QA L 100% ➡️ status update
Interface Development 4 Discovery Dev QA 6 83,3%
Initial Definition / Discovery BE Discovery Discovery S 100% ONERES bookings over API
Interface to ONERES (API bookings) BE Dev QA L 80% Changed, Delayed not on critical path
Interface DAS via Kafka BE Dev QA M 80% Additional work not on critical path
LH Partner Creation Portal 8 Dev QA 8 80%
Dev:Partner creation processes Mixed Dev QA L 95% ➡️ status update, in testing
Full project (100%) 100 Discovery & Dev preparations Core Dev Core QA Int. Testing Golive 87,4%
Additional work 11
Full test servers in NUE with new B-Op-Infra Admin

BE

Deployment M 100%
Login&Registration Extensions for PAX & Botprotection Mixed M 100% in testing
Interface to ONERES (GAV) Specification BE S 100%
Interface to ONERES (GAV) Implementation Mixed S 50%
SCHED-Connect Specification BE S 100%
SCHED-Connect Implementation Mixed M 80%
Communication templates and implementation Mgmt, mixed DEV & QA M 90% ➡️ status update
Task templates and implementation Mgmt, mixed DEV & QA S 10% ➡️ status update
Document templates and implementation Mgmt, mixed DEV & QA S 0%
Performed work 71,2%

Step-by-Step to success

  • Starting from 1st of July 2025, the core development takes place, which should be finished by end of February (30 weeks) including internal Q&A. There are 11 development milestones, which are scheduled. See article LHG:SARA Project Phase 1 - Current presentation milestones It is not expected, that everything runs flawlessly until then, but all building blocks should be there and just rework and bugfixing should happen from there.
  • From 1st of March 2026, the full integration testing should commence and non-essential development tasks are scheduled Acceptance tests with LHG will commence with a timeframe of roughly 10 week until the system is ready for production.
  • Goal is to reach Go-Live readiness in May 2026

Project history & updates

See also