LHG:SARA Project: Difference between revisions

From Kordeus Wiki
Jump to navigation Jump to search
Stefanseiler (talk | contribs)
Jagodapejovic (talk | contribs)
Line 258: Line 258:
|
|
|S
|S
|20%
|100%
|26.11. Revision after additional feedback {{Yellow-Tag|YellowText=Additional work}}
|
|-
|-
|Minor extensions during feedback sessions (limitations)
|Minor extensions during feedback sessions (limitations)
Line 284: Line 284:
|
|
|S
|S
|20%
|100%
|26.11. NEW - Travel services feedback
|
|-
|-
|Automation Engine Admin Open
|Automation Engine Admin Open
Line 308: Line 308:
|
|
|L
|L
|5%
|15%
|{{Yellow-Tag|YellowText=Ticket size changed}}
|status update
|-
|-
| colspan="25" |
| colspan="25" |
Line 423: Line 423:
|
|
|M
|M
|
|?
|{{Yellow-Tag|YellowText=Additional work}}, Spec done 27.11.  
|{{Yellow-Tag|YellowText=Additional work}}, Spec done 27.11.  
|-
|-
Line 558: Line 558:
|
|
|XXL
|XXL
|25%
|30%
|{{Yellow-Tag|YellowText=Ticket size changed}}
|status update
|-
|-
|[[Dev:SLH - TravelServiceManagementEcosystem|SLH - TravelServiceManagementEcosystem]]
|[[Dev:SLH - TravelServiceManagementEcosystem|SLH - TravelServiceManagementEcosystem]]
Line 579: Line 579:
|
|
|XL
|XL
|40%
|45%
|{{Yellow-Tag|YellowText=Ticket size changed}}
|status update
|-
|-
|[[SARA.ProcessAutomationEngine]]
|[[SARA.ProcessAutomationEngine]]
Line 680: Line 680:
|
|
|M
|M
|10%
|25%
|
|status update
|-
|-
| colspan="25" |
| colspan="25" |

Revision as of 09:36, 6 January 2026

Phase 1 - SARA Fundamental

Current Project Plan

Dev

Focus

2024 2025 2026 Est.

Size

Dev

Progress

External Dep.

Notes

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Peparatory work 4 Discovery Discovery 100%
Kickoff / Initially planned discovery Def S 100%
Architecture & Shared Logic Hubs Discovery Re-Discovery XL 100% Additional project phase
Administration tools 8 Dis. Dev Discovery Dev QA Dev QA 75,2%
Definition / Discovery Def Dev Re-Discovery L 100% Additional project phase
LH Admininistration Tools Mixed Dev QA L 100%
MOC Administration Tools Mixed Dev QA L 100%
SLHs (TravelCarrierDataDistribution & OperationCenterPAXExchange BE Dev QA L 100% Ticket size changed over time
Minor extensions during further discovery Mixed Dev QA S 100%
SLH - TravelCDDD, SLH - OCPAXE extensions due to feedback S 100%
Minor extensions during feedback sessions (limitations) Mixed S 100%
Automation Engine Admin Open Mixed Dev QA L 15% status update
Passenger Portals 28 Dev QA Dev QA 76,9%
PAX funcationality in PAX.Portal for LH FE & BE Dev QA XL 100% ✅ Ready for testing
SLH - PortalUsageInteraction BE Dev L 100% ✅ Ready for testing
Full PAX.Portal for Discover FE Dev QA M 90%
Direct Login&Registration for PAX & Botprotection Mixed M ? Additional work, Spec done 27.11.
TP-Employee features Mixed Dev Conf QA M 60% Delayed
SARA.Core 40 Dis. Discovery Dev QA 49,3%
Initial definition of BE (like SWISS) Mgmt Def S 100%
Full SAM process discovery Mgmt Discovery XL 100% Additional project phase
UI/UX Iteration MgMt Dev M 100% Additional project phase
SARA.Core App Development Mixed Dev XXL 30% status update
SLH - TravelServiceManagementEcosystem BE Dev XL 45% status update
SARA.ProcessAutomationEngine BE Dev QA XL 0% Ticket size changed
LH EntraID BE Conf QA S 0% Requires board
SARA.DeliveryPartnerPortal 8 Discovery Dev QA 10%
Delivery Partner Portal Mixed Discovery Dev QA M 25% status update
Interface Development 4 Discovery Dev QA 30%
Initial Definition / Discovery BE Discovery Discovery S 100% ONERES bookings over API
Interface to ONERES (API bookings) BE Dev QA L 20% Delayed not on critical path
Interface DAS via Kafka BE Dev QA M 10% Additional work
Interface to ONERES (GAV, Flightplan) BE 5% Additional work Next project phase !?
Interface to SIRAX BE 0% Next project phase !?
SHED-Connect
LH Partner Creation Portal 8 Dev QA 0%
Dev:Partner creation processes Mixed Dev QA L 0%
Full project 100 Discovery & Dev preparations Core Dev Core QA Integration Testing Golive 53,3%

Step-by-Step to success

  • Starting from 1st of July 2025, the core development takes place, which should be finished by end of February (30 weeks) including internal Q&A. There are 11 development milestones, which are scheduled. See article LHG:SARA Project Phase 1 - Current presentation milestones It is not expected, that everything runs flawlessly until then, but all building blocks should be there and just rework and bugfixing should happen from there.
  • From 1st of March 2026, the full integration testing should commence and non-essential development tasks are scheduled Acceptance tests with LHG will commence with a timeframe of roughly 10 week until the system is ready for production.
  • Goal is that from May 2026, LHG can press the start button whenever they want to.

Project history & updates