Phase 1 - SARA Fundamental

Current Project Plan

Dev

Focus

2024 2025 2026 Est.

Size

Dev

Progress

External Dep.

Notes

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Peparatory work 4 Discovery Discovery 100%
Kickoff / Initially planned discovery Def S 100%
Architecture & Shared Logic Hubs Discovery Re-Discovery XL 100%
Administration tools 8 Dis. Dev Discovery Dev QA Dev QA Dev QA Dev QA 85,0%
Definition / Discovery Def Dev Re-Discovery L 100%
LH Admininistration Tools Mixed Dev QA L 100%
MOC Administration Tools Mixed Dev QA L 100%
SLHs (TravelCarrierDataDistribution & OperationCenterPAXExchange BE Dev QA L 100% Ticket size changed over time
Minor extensions during further discovery Mixed Dev QA S 100%
SLH - TravelCDDD

SLH - OCPAXE extensions due to feedback

Dev S 100%
Minor extensions during feedback sessions (limitations) Mixed Dev QA S 100%
Automation Engine Admin Mixed Dev Dev QA L 15% Repriorized
Passenger Portals 28 Dev QA Dev QA 90,9%
PAX funcationality in PAX.Portal for LH FE & BE Dev QA XL 100%
SLH - PortalUsageInteraction BE Dev L 100%
Full PAX.Portal for Discover FE Dev QA M 90%
TP-Employee features Mixed Dev Conf QA M 60% Delayed
SARA.Core 40 Dis. Discovery Dev QA 54,0% Delayed (2 weeks?)
Initial definition of BE (like SWISS) Mgmt Def S 100%
Full SAM process discovery Mgmt Discovery XL 100% Additional project phase
UI/UX Iteration MgMt Dev M 100% Additional project phase
SARA.Core App Development Mixed Dev XXL 40% status update
SLH - TravelServiceManagementEcosystem BE Dev XL 45% status update
SARA.ProcessAutomationEngine BE Dev QA XL 0% Ticket size changed
SARA.DeliveryPartnerPortal 8 Discovery Dev QA 25,0%
Delivery Partner Portal Mixed Discovery Dev QA M 25% status update
Interface Development 4 Discovery Dev QA 43,3%
Initial Definition / Discovery BE Discovery Discovery S 100% ONERES bookings over API
Interface to ONERES (API bookings) BE Dev QA L 40% Delayed not on critical path
Interface DAS via Kafka BE Dev QA M 20% Additional work
LH Partner Creation Portal 8 Dev QA 20%
Dev:Partner creation processes Mixed Dev QA L 20% Preponed (Add capacity)
Full project 100 Discovery & Dev preparations Core Dev Core QA Integration Testing Golive 53,3%
Additional steps
Full test servers in NUE with

new B-Op-Infra

Admin

BE

Deployment M 80% 06.01.2026 - new
Login&Registration Extensions (not only TravelID)

for PAX & Botprotection

Mixed M ? Additional work, Spec done 27.11.
Interface to ONERES (GAV) Mixed S 5% Additional work Next project phase !?
Interface to SIRAX Mixed M 0% Next project phase !?
SCHED-Connect Specification S
8 20,6%

Step-by-Step to success

  • Starting from 1st of July 2025, the core development takes place, which should be finished by end of February (30 weeks) including internal Q&A. There are 11 development milestones, which are scheduled. See article LHG:SARA Project Phase 1 - Current presentation milestones It is not expected, that everything runs flawlessly until then, but all building blocks should be there and just rework and bugfixing should happen from there.
  • From 1st of March 2026, the full integration testing should commence and non-essential development tasks are scheduled Acceptance tests with LHG will commence with a timeframe of roughly 10 week until the system is ready for production.
  • Goal is that from May 2026, LHG can press the start button whenever they want to.