LHG:SARA Project: Difference between revisions

From Kordeus Wiki
Jump to navigation Jump to search
Stefanseiler (talk | contribs)
Stefanseiler (talk | contribs)
Line 364: Line 364:
!
!
|-
|-
|MOC Detailed Process Analysis {{Red-Tag|Text=not planned}}
|MOC Detailed Process Analysis
|Mgmt
|Mgmt
|
|
|
|
|
|
| colspan="6" |[[LHG:Unplanned Discovery Sessions|Discovery]]
| colspan="6" |Discovery
|
|
|
|

Revision as of 06:01, 23 June 2025

Phase 1 - SARA Fundamental

Current Project Plan

Dev

Focus

Est. Size 2024 2025 2026 Est.

Size

Progress External Dep.

Notes

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Kickoff / Initially planned discovery Def S 100% 3 days pre-order
Architecture & Shared Logic Hubs Discovery Re-Discovery 100% re-discovery not planned
Administration tools Dev Discovery Dev Q&A Dev Q&A 70%
Definition / Discovery Def Discovery L 100%
LH Admininistration Tools Mixed Dev Q&A L 80%
MOC Administration Tools Mixed Dev Q&A XL 40%
SLH - TravelCarrierDataDistribution BE Dev Q&A M 0% Carrier digital <--> PAX Portal Digitals, Travel Service Operation Center Digitals
Minor extensions during further discovery Mixed Dev Q&A S 0%
SARA.PAXPortal Dev Q&A Dev Q&A 10%
PAX funcationality in PAXPortal for LH FE & BE Dev Q&A XL 20% Interaction with Passenger Digital and Travel Partner Digital
SLH - PortalUsageInteraction BE Dev L 0% PAX Portal Digitals <-> Passenger Digitals, Travel Partner Digitals
Travel agent functionality of SARA.PAXPortal Mixed Dev Conf Q&A M 0% TravelID / Travelagent-Login
Full PAXPortal for Discover FE Dev Q&A M 0%
SARA.Core Unplanned discovery Dev Q&A 20%
MOC Detailed Process Analysis Mgmt Discovery XL 80% main reason for delay, 28 AT days extra work (whole team)
SARA.Core App Development FE/BE Dev XL 0%
SLH - TravelServiceManagementEcosystem BE Dev L 0% Travel Service Operation Center <-> Passenger Digitals, Delivery Partner Digitals
SARA.ProcessAutomationEngine BE Dev Q&A Dev Q&A XL 0%
LH EntraID BE Conf Q&A S 0%
SARA.DeliveryPartnerPortal Discovery Dev Q&A 20%
Delivery Partner Portal Mixed Discovery Dev Q&A M 10%
Interface Development Discovery Dev Q&A 15%
Definition / Discovery BE Discovery S 60%
Interface to ONERES BE Dev Q&A L 0% LH Int Ready, Req BTeam
Interface to SIRAX BE Dev Q&A S 0% LH Int Ready, Req BTeam
LH Partner Creation Portal Dev Q&A 0%
SARA.PartnerCreationPortal Mixed Dev Q&A L 0%
Full project Discovery & Dev preparations Core Dev Core Q&A Integration Testing Golive

Step-by-Step to success

From 1st of July until core Q&A finished are 30 weeks for core development. There are 11 development milestones, which are scheduled in the article LHG:SARA Project Phase 1 - Current presentation milestones

It is not expected, that everything runs flawlessly until then, but from February, acceptance tests with LHG will commence with a timeframe of roughly 10 week until the system is ready for production. Goal is that from May LHG can press the start button whenever they want to.

Project history & updates

See also