Dev:Internal meeting notes with team (LH-Project) - 20.05.
Jump to navigation
Jump to search
This article holds central information on internal meetings in combination with Kordeus.PAX development through the Lufthansa MOC project
20.05. 10:00 (M, J, G, S)
- Backend development requires clarification on SLHs - concrete estimation is hard
- Abtract controllers will be there by End Of June
- Stefan explained the concept and the state of development and what this means to dev.
- Full scale dev can only start after discovery completion, before that (June) preparations and frontend-prework as Design-Figma is reached
- Updated project plan from:
- Dev perspective: total DEV (no QA around 14-20 weeks)! Q&A 1 month internal? 2-3 months integration testing with Lufthansa?
- Arch perspective: Dev ~ 6mo, Q&A ~ 4 mo, Realistic GoLive ~ Mar to May